Change Order No. 1 to Contract No. 135514 between the City of Tulsa and Becco Contractors, Inc., for Project No. 144018, for Bicycle and Pedestrian Plans Citywide, Phase 3, along E. 6th St. - S. Boulder Ave. to S. Delaware Ave.; Charles Page Blvd. - S. 65th W. Ave. to Houston Ave.; S. Houston Ave. - Riverside Dr. to Heavy Traffic Way; Southwest Blvd. - Riverside Dr. to W. 48th St. S. in the amount of zero dollars ($0.00), and adding ninety-one (91) calendar days to the contract due to weather delays, plan modifications, and coordination with City of Tulsa crews. (CD-1,2,4) [UED 3/30/22; CC 4/6/22]