Change Order No. 1 to Contract No. 135416 between the City of Tulsa and Ellsworth Construction, LLC, for Project No. 144857 in the amount of twenty-four thousand, thirty dollars ($24,030.00) and adding one hundred sixty (160) calendar days due to groundwater encountered onsite, roadway design changes resulting from subgrade failures, weather, and design changes on portions of E. 70th St. resulting in full depth reconstruction for Arterial Street Rehabilitation on S. Oswego Ave. and E. 71st St. (CD-8) [PW 11/16/22; CC 11/30/22]