Consideration and possible approval, adoption, denial, amendment or revision of Change Order No. 1 to Contract No. 135936 between the City of Tulsa and Becco Contractors, Inc. for Project Nos. 2036A0008Z, 10Z, 11Z, 12Z, and TMUA ES2020-02 in the amount of fifty-three thousand, one hundred dollars and eighty cents ($53,100.80) and adding forty (40) calendar days due to recommended weather days as well as additional work required to remove and replace three (3) brick stormwater inlets on Edison St. [PW 3/13/24; CC 3/27/24]