- Sewer Line Installation on East 21st Street, from South Peoria Avenue to Riverside Drive, to Begin on Monday, April 20 2026
Sewer Line Installation on East 21st Street, from South Peoria Avenue to Riverside Drive, to Begin on Monday, April 20
4/17/2026
A road rehabilitation and sewer line installation project on East 21st Street from South Peoria Avenue to Riverside Drive is scheduled to begin on Monday, April 20.
The project will be completed in three phases, with East 21st Street open to two-way traffic in the westbound lanes throughout construction.
During the first phase of the project, construction will begin in the eastbound lanes of East 21st Street between Riverside Drive and South Detroit Avenue. During this time, South Main Street between East 21st Street and East 22nd Street will be closed to thru traffic.
In the second phase, work will move east between South Cincinnati Avenue and South Norfolk Avenue. In the final phase, construction will continue east between South Madison Avenue and South Peoria Avenue.
Each phase is expected to last approximately 70 days.
During construction, drivers are encouraged to slow down and follow all posted traffic signs.
The City of Tulsa has contracted with Triangle Construction and Utility for this $3,484,000 TMUA Water Operating Fund project, and construction is scheduled for completion before the end of the year.
Area neighbors have already been notified, and a public meeting was held to discuss project specifics in December at the Centennial Center in Veterans Park.
Additional Street Projects
Drivers should also be aware of several other street improvement projects currently underway or beginning soon that may impact traffic.
Notable projects that are active or are scheduled to begin soon include:
- Gilcrease Museum Road, Admiral to Pine - The street reconstruction project is 40% complete, with Gilcrease Museum Road currently closed from West Edison Street to West Pine Street. The City of Tulsa has contracted with Becco Contractors for this $25 million project funded through the Improve Our Tulsa 2 sales tax extension. Construction is scheduled for completion in late 2026.
- 91st, Memorial to Mingo – The street widening project is over halfway done, with two-way traffic currently being diverted to the northbound side of 91st. The City of Tulsa has contracted with Tri-Star LLC for this $12.8 million project funded through the Improve Our Tulsa 2 sales tax extension. Construction is scheduled for completion in early 2027.
- Utica, Admiral to Pine - This street rehabilitation and waterline replacement project is almost halfway complete, with traffic currently being reduced to one lane going northbound. The City of Tulsa has contracted with Becco Contractors for this $15,137,000 Improve Our Tulsa project. Construction is scheduled for completion in summer of 2027, weather permitting.
- 91st, Harvard to Yale - This street rehabilitation and waterline reconstruction project has just started, with two-way traffic currently being diverted to the eastbound lanes. The City of Tulsa has contracted with Paragon Contractors for this $4,985,000 Improve our Tulsa 2 project. Construction is scheduled for completion in late 2026, weather permitting.
- 15th, Lewis to Harvard - This street rehabilitation project has just begun, with two-way traffic currently being diverted to the westbound lanes. The City of Tulsa has contracted with Becco Contractors for this $3,421,000 Improve Our Tulsa project. Construction is scheduled for completion in spring of 2027, weather permitting.
- Utica, 11th to 15th - This street rehabilitation and waterline replacement project began in March, with traffic currently being diverted to the southbound lanes. The City has contracted with Becco Contractors for this $4,987,000 Improve our Tulsa project. Construction is scheduled for completion late 2026, weather permitting.
- Detroit, Archer to 13th – A street rehabilitation project will begin in May on North Detroit Avenue between East Archer and East 13th Streets. The City has contracted with Becco Contractors for this $2,487,000 Improve our Tulsa project. Construction is scheduled for completion in early 2027, weather permitting. More information will be made available soon.
- ]4th, Detroit to Lansing – A street rehabilitation and waterline replacement will begin in May on East 4th Street between South Detroit and South Lansing Avenues. The City has contracted with Tri-Star Contractors for this $3,197,000 Improve our Tulsa project. Construction is scheduled for completion in spring of 2027, weather permitting. More information will be made available soon.